Top Roof Section Module Build Instructions
Script
- Cut 16' long members to 16' exactly.
- Mark location of purlins 4' on center
- Cut 4 purlins and 2 end caps for roof frame - fitted between long 16' members so that the panel is 3' wide. Note that we are not using plywood here.
- Screw 2 long members and 2 end caps together using [3] 3" screws
- Screw in purlins at marked locations
- Invert on sawhorses and staple tyvek base layer upon which insulation will sit
- Re-invert to right-side-up and insert insulation
- Cover the top of panel with Tyvek as a moisture barrier under metal roofing. Note: do not install metal roofing - it is not possible to line up the seams this way, so roof metal goes on last.
Tools and Materials
- 3/8" Stapler
- Miter saw
- Pencil
- Metal roofing screws (for install)
- Tyvek
- 2x6s
- Roof metal - (after roof is in place)
- Flashing - (after roof is in place)
- Roof metal ridge seal foam
- Insulation
- Pro-Rib vented seal - ? - [1]
- Pro-Rib outside closure - [2]
- Pro-Rib inside closure - [3]
Visual Animation in Sketchup
See scenes in this Sketchup animation.
Download file - File:Toproofbuild.skp (uses wiki version control)
Warehouse version -may not be updated - Warehouse has no versioning: